Cloudera Upgrade + Hue Document Cleanup Question

Hi,

I'm going to be upgrading our CM/CDH 5.14 cluster to 5.16.  I've noticed a new step named "Hue Document cleanup" (https://www.cloudera.com/documentation/enterprise/upgrade/topics/ug_cdh_upgrade.html#cdh_upgrade5)

Looking at the estimate given (1 minute per 1000 rows), this would take around 3 hours at best on my cluster (MySQL backend).

Can these scripts be run with theh cluster still operational and will if affect anything?  Ideally I would like to run this outside of my maintenance window to save time, but can only do so if the cluster will still be in a usable state.

Contributor
Posts: 48
Registered: ‎04-26-2017

Re: Cloudera Upgrade + Hue Document Cleanup Question

Incase anyone comes across this, it only took around 3 seconds per 1000 rows.