Hi,

 

This is the 2nd time i am trying to install CDH enterprise trial edition. It stucked at 30% for more than 6 hrs. I am installing it on 3 nodes on Redhat 6 64bits.

 

I suspect it was the disk space in the manager or the nodes, but the below is the result of the df in nodes and the CDM. How do I troubleshoot?

 

Filesystem           1K-blocks      Used Available Use% Mounted on
/dev/mapper/volGroup00-LogVol01
                             8051120   3536004  4106132  47% /
tmpfs                    1962440             0   1962440   0% /dev/shm
/dev/sda1               198337     68944    119153  37% /boot

step 4 of 5

Cluster Installation

Installing Selected Parcels

SOLR 1.0.0-1.cdh 4.3.0.p0.4           30%

IMPALA 1.1.1-1.p0.17                      30%

CDH 4.4.0-1.cdh4.4.0.p0,39            30%

 

 

 

Posts: 416
Topics: 51
Kudos: 89
Solutions: 49
Registered: ‎06-26-2013

Re: Cluster installation stuck at 30%

Are these, by any chance, virtual machines on a single parent host?  I've had the same problem before as the downloading of all the CDH parcels to all three machines at once saturated my network/IO on my physical machine.  I ended up installing only the master host first, then adding the additional two hosts one-by-one later.  

New Contributor
Posts: 4
Registered: ‎10-14-2013

Re: Cluster installation stuck at 30%

Those are VMs in the cloud. I wouldn't know. I think I will try node by node
New Contributor
Posts: 4
Registered: ‎10-14-2013

Re: Cluster installation stuck at 30%

tried it on single node. still the same. stuck at 30%