Using Ambari how do we change the YARN configuration setting "yarn.resourcemanager.max-completed-applications". We are using HDP 2.4. Thanks

New Contributor
 
1 REPLY 1

You would add the yarn.resourcemanager.max-completed-applications property to "custom yarn-site" in Ambari -> Yarn -> Configs. It is not set by default and YARN works with a default value of 10000.