Hi All,

 

1. What is "Rows available" in Query Timeline of Impala query mean? what is Impala doing at this stage?

2. Is there a place where I can find an explanation of all the query profile metrics?

 

Thanks

 

1 ACCEPTED SOLUTION

Accepted Solutions

Re: Impala "Rows available" in Query Timeline

Expert Contributor

Hi @hores

1- You are welcome.
2- Unfortunaly, I do a lot of searchs and it seems like there is no more depth explications about the queries profile metrics. What I advice you is when do you have a problem to understand one of it, try to communicate it with the community to get more explanations.


Good luck.

3 REPLIES 3

Re: Impala "Rows available" in Query Timeline

Expert Contributor

Hi @hores

1- I thing "Rows available" time, is the time that impala taked to execute the query and prepare the results to be fetched, it's just before "First row fetched".

2- May be this link about Monitoring Impala Queries can help you.

Re: Impala "Rows available" in Query Timeline

Explorer

HI @AcharkiMed,

 

1. Thanks!

2. Thanks, but all the explanations in the link you sent I get  when hovering with the mouse over the metrics,

but I was asking about the metrics in Query Fragments section in Impala Cloudera .

 

Re: Impala "Rows available" in Query Timeline

Expert Contributor

Hi @hores

1- You are welcome.
2- Unfortunaly, I do a lot of searchs and it seems like there is no more depth explications about the queries profile metrics. What I advice you is when do you have a problem to understand one of it, try to communicate it with the community to get more explanations.